An event that must occur in order for a party's duty to arise is called a(n) ________________.

Respuesta :

meerkat18
meerkat18 meerkat18
  • 05-12-2017
This is what they call condition precedent. The party's task to perform arise after a specific event happens. However, when the event never happens, the duty of the party to perform will never arise. The parties are discharged from the contract. 
Answer Link

Otras preguntas

How does Victor Frankenstein's story parallel the story of Prometheus and Pandora? O A. Both Victor and Zeus used lightning to give life to their creations O B.
The call of the wild quote and narrative
Which quotation from the passage encompasses the climax of the story? O “Then [the Queen) took twenty mattresses and laid them on the pea." "In the morning she
5 ingredients of creativity are time alone, curiousity
A quality manager is developing a regression model to predict the total number of defects as a function of the day of week the item is produced. Production runs
2. What must be done to carbon dioxide gas to change it to a solid?. 3. Which is colder, dry ice or carbon dioxide gas? If dry ice is placed in water, we see bu
"How did technology play a role in opening Southeast Asia and the Pacific to foreign influence?"
What is 6+3x(4 1/2 -7 3/8) -7 =?
Can anyone help me with Question 2 please?
The period of European history after the fall of Rome and the beginning of the renaissance