A person can do a job in 6 days. Another can do the same job in 4 days. If they work together, how long do they need to finish the job?

Respuesta :

wegnerkolmp2741o
wegnerkolmp2741o wegnerkolmp2741o
  • 25-07-2020

Answer:

2.4 days

Step-by-step explanation:

Time working together,t ,is

1/t = 1/a+ 1/b  where a and b is the times working alone

1/t = 1/4 + 1/6

Multiply each side by 12t to clear the fractions

12t( 1/t )= 12t(1/4 + 1/6)

12 = 3t+2t

12 = 5t

Divide by 5

12/5 = 5t/5

2 2/5 =t

2.4 days

Answer Link
635624
635624 635624
  • 25-07-2020

Answer:

2.4 days

Step-by-step explanation:

i just took a test and got a 100%

Answer Link

Otras preguntas

Which descriptions refer to short-range forecast
With all his gear Neil Armstrong wait 360 pounds on earth when he landed on the moon he weighed 60 pounds why
Please help me with this problem
Kyra has a rock collection.When she puts her rocks into 2 equal piles,there are no rocks left over.When she puts her rocks into 3 equal piles ,there are still
Which philosophical assumption is best supported by this selection from Jane eyre? (Picture is attached)
helppppppppppppppppppppppppppppp
Which city is located at approximately 38° n, -9° w on the map above? A. london b. budapest c. rome d. lisbon
Mildew is a fungus that grows in wet areas and can slowly grow from
Use addition properties and strategies to find the sum..1.)34+62+51+46=? 2.)27+68+43=? 3.)42+36+18=? 4.)74+35+16+45=?
What types of evidence support inferences about characters in a play?