Qn.11 plz help this with step ​

Qn11 plz help this with step class=

Respuesta :

salatulmaghrib
salatulmaghrib salatulmaghrib
  • 25-07-2019
The answer is 7.5 days
explanation:
80 is four times 20.
80 people should be able to do the job four times faster than 20 people.
So, they should take 1/4 the time.
If 20 people take 30 days, 80 people should take 30/4=7.5 days.
**
simpler explanation:
30*20/80=7.5
Answer Link

Otras preguntas

how does the water get to the leaves in the tops of the tallest trees against the force of gravity?
Which of the following is not a listed provision in any of the treaties with Tribal Nations? Select the best answer choice. A)Friendship and military alliances
Prions are proteins that act as an infectious agent. They cause a variety of diseases, including "mad cow" disease. Prions cannot produce more potions on their
Which of the following is not a listed provision in any of the treaties with Tribal Nations? Select the best answer choice. A)Friendship and military alliances
Which of the following describes a structure that both prokaryotic and eukaryotic cells have in common?
What is the solution to the compound inequality?
Which organs are responsible for producing fluid to give sperm nourishment and motility?
In 1668, Francesco Redi conducted an experiment with jars of meat. This experiment was noteworthy because it _____.
Tay-Sachs disease is prominent among African-Americans Italian-Americans Native Americans Jewish-Americans
How do I do this? Can someone fill in the blanks