p can do a piece of work in 50 days, q in 40 days and r in 30 days respectively. If r is assisted by p on one day and by q on the next day alternately then the work gets complete?
o 17 32/35 days
o 19 ⅔ days
o 16 31/37 days
o 16 31/37 days

Respuesta :

Otras preguntas

In france what was the absote monarchs political structure called?
I need 1,2,3,4,5,!! Help please
Everyone in the class is under 13 years old. Let x be the age of a person in the class.
Does the biosphere have clear boundaries? explain why or why not.
Two trains leave the station at the same time, one heading west and the other east. The westbound train travels 12 miles per hour faster than the eastbound trai
The Holy Roman Empire was created by?
What is an energy issue our society faces today?
PLEASE HELP!!! ______________ was the first tonal method to be used enabling half-tones to be produced. a. engraving b. mezzotint c. drypoint
There are 8 pencils in a package. How many packages will be needed for 28 children if each child gets 4
How are water systems important to the Canadian economy?